MARPORT MODERNIZATION AND EXPANSION PROJECT BERTH-7 MODULE-14 AND CONNECTING DOLPHIN CONSTRUCTION WORKS
Project Name | Marport Modernization and Expansion Project Berth-7 Module-14 and Connecting Dolphin Construction Works |
Project Location | Beylikduzu-Istanbul, TURKEY |
Employer | Marport Liman Isletmeleri San. ve Ti̇c. A.S. |
Main Contractor | KORFEZDENIZ INSAAT TAAH. SAN. VE TIC. LTD. STI. |
Commencement | 07.11.2021 |
PROJECT SCOPE
-
Berth-7 Module-14 Construction Work (90x40m):
- Steel pile driving works (Driving of 127 nos, Ø1371.6 mm, t=20 mm steel tubular piles)
- Construction of superstructure (reinforced concrete and reinforcement works)
- Backfilling works
- Cathodic protection in steel tubular piles
- Dynamic capacity test on piles (PDA test)
- Retaining wall construction
- Fire pump station construction
- Installation of marine furniture (Fenders, bollards, rails, stowage pins, tie-downs and panzerbelt systems)
- Module-13 bored pile works-(Construction of bored piles of Ø1200 mm by total length of 2170 meter, (43 pcs)).
Connecting Dolphin and Catway Construction Works:
- Steel pile driving works (Driving of 9 nos, Ø1625,6 mm, t=24 mm steel tubular piles)
- Construction of superstructure (reinforced concrete and reinforcement works)
- Cathodic protection in steel tubular piles
- Installation of marine furniture (Manufacturing and installation of catwalk)