MARPORT MODERNIZATION AND EXPANSION PROJECT BERTH-7 MODULE-14 AND CONNECTING DOLPHIN CONSTRUCTION WORKS

Project Name Marport Modernization and Expansion Project Berth-7 Module-14 and Connecting Dolphin Construction Works
Project Location Beylikduzu-Istanbul, TURKEY
Employer Marport Liman Isletmeleri San. ve Ti̇c. A.S.
Main Contractor KORFEZDENIZ INSAAT TAAH. SAN. VE TIC. LTD. STI.
Commencement 07.11.2021
PROJECT SCOPE
  • Berth-7 Module-14 Construction Work (90x40m):

    • Steel pile driving works (Driving of 127 nos, Ø1371.6 mm, t=20 mm steel tubular piles)
    • Construction of superstructure (reinforced concrete and reinforcement works)
    • Backfilling works
    • Cathodic protection in steel tubular piles
    • Dynamic capacity test on piles (PDA test)
    • Retaining wall construction
    • Fire pump station construction
    • Installation of marine furniture (Fenders, bollards, rails, stowage pins, tie-downs and panzerbelt systems)
    • Module-13 bored pile works-(Construction of bored piles of Ø1200 mm by total length of 2170 meter, (43 pcs)).

    Connecting Dolphin and Catway Construction Works:

    • Steel pile driving works (Driving of 9 nos, Ø1625,6 mm, t=24 mm steel tubular piles)
    • Construction of superstructure (reinforced concrete and reinforcement works)
    • Cathodic protection in steel tubular piles
    • Installation of marine furniture (Manufacturing and installation of catwalk)