SAFI DERINCE INTERNATIONAL PORT PHASE-1 EXTENSION PROJECT
Employer | SAFI DERINCE INTERNATION PORT MANAGEMENT INC. CO. |
Project Name | SAFI DERINCE INTERNATIONAL PORT PHASE-1 EXTENSION PROJECT |
Contractor | KORFEZDENIZ INSAAT TAAH. SAN. VE TIC. LTD. STI. |
Start Date | 30 June 2017 |
PROJECT SCOPE
- B Type Modules:
- 508 nos steel tubular piles with Ø1422,4 mm OD and 18-20mm thickness (Approximately total legth22.860 m
- 450 m x 37 m dimensioned harbour construction with precast and cast in situ concrete works
- Reclamation and slope protection works
- 2X450 m Ship to Shore(STS) Crane Rail assembly
- A2 Type Modules:
- 202 adet Ø1016,0 mm t=16 mm çelik boru kazık çakımı (Yaklaşık 7.272 m)
- 202 nos steel tubular piles with Ø1016,0 mm OD and 16mm thickness (Approximately total legth 7.272 m)
- 240 m x 24 m dimensioned harbour construction with precast and cast in situ concrete works
- Reclamation and slope protection Works
- A1 Type Modules
- 84 adet Ø914,4 mm t=14 mm çelik boru kazık çakımı (Yaklaşık 2.856,00 m
- 160 m x 14 m dimensioned harbour construction with precast and cast in situ concrete works
- Reclamation and slope protection Works
- Preparation of 7500 ton steel reinforcement for construction
- Casting 62.000m³ concrete for construction