1915 CANAKKALE BRIDGE WET-DOCK AND LOGISTICS JETTY
CONSTRUCTION PROJECT

 

Project Name 1915 Çanakkale Bridge Wet Dock Construction
Project Location Çanakkale / TÜRKİYE
Employer ÇOKİYİ A.Ş.
Main Contractor DLSY (DAELIM-LİMAK-SK-YAPI MERKEZİ) ADİ ORTAKLIĞI
Subcontractor  KÖRFEZDENİZ İNŞAAT TAAH. SAN. VE TİC. LTD. ŞTİ.
Commencement 16.01. 2018
Completion 10. 01. 2019
PROJECT SCOPE
  • Construction of access bridge and 4 no’s of dolphins
  • Driving 139 no’s steel tubular piles 1600 mm OD, 25 mm WT with various length between 34m-52,5 m
  • Execution of Pile Dynamic Tests (PDA) on 15 project piles
  • Manufacturing and installation of steel super structure consist of HEB1000/HEB340/HEB300/HEB200 profiles and various steel plates
  • Manufacturing and installation of 190 no’s precast slabs
  • Casting concrete 2772 m3
  • Fabrication of Steel Reinforcement 400 ton
  • Installation of 3684 no’s Ø19/300 mm stud nails
  • Installation of 55262 no’s Ø19/150 mm stud nails
  • Installation of 20 no’s marine fenders
  • Supply and installation of 11 no’s 35t/50t marine bollards
  • Installation of 32 no’s Mooring/Berthing Winch, Sheave, Swivel head and Wire Stopper