Project Information

  • Status Completed
  • Location Aliağa, İzmir, Türkiye
  • Year 12 Kasım 2016

Contact Us

Scope of Work

*4,983 m² jetty and dolphin construction

*Driving of 334 pcs Ø1168 mm, t=19 mm, up to 35 m (max) long steel pipe piles using our equipment

*350 m jetty construction

*46×25 m loading platform construction

*2 pcs 18×12.5 m loop discharge structures

*9 dolphins (max 15×28×2.5 m)

*13 catwalk dolphins

*11 pcs 150-ton quick release hooks

*6 fenders

*16 catwalks installation

*6,675 m² formwork

*1,500 tons rebar installation

*11,416 m³ concrete pouring